Obligation to measure and report water quality

Last updated on November 5, 2024.

1.Obligation to measure water quality (Article 12-12 of the Act (outside site), Ministerial Ordinance Article 15 (outside site), Ordinance Article 11 (outside site), Regulations Article 16 (outside site), Article 16-2 (outside site) (outside site)))

Business establishments that have specific facilities or abatement facilities must measure the water quality in the following ways, record the results, and save them.

(a) The measurement method should be performed according to the measurement method specified in the ministerial ordinance on the certification method of sewage water quality.

(b) For the number of measurements, please perform the number specified in the regulations for each item and the amount of drainage. The number of measurements for each measurement item is as shown in the following table.

(c) Samples for measurement should be taken from the middle part of the water depth at the time when the quality of the sewage to be measured is estimated to be the worst.

(d) Samples should be collected at the outlets and exits of abatement facilities.
(Ministry Ordinance Article 15 No. 4 (External Site), Ordinance Article 11 (External Site))

(o) Please keep the measurement results for 5 years.
※Water quality measurement record table: Emission outlets → Style 13th (word: 25KB), exit of abatement facilities, etc. → No. 11 style (word: 15KB)

2.Duty to report (Article 39-2 of the Act (outside site), ordinance Article 12 (outside site))
The installer of the specific facility and the installer of the abatement facility have a duty to report the necessary limit from Yokohama City to properly manage the sewer. Even if the drainage meets the water quality standards due to the establishment of an abatement facility by a non-specific business establishment, a report based on the ordinance must be made as long as the abatement facility is installed.

Penalties may be applied to those who do not report or make false reports in violation of this provision. (Act Article 49 No. 5 (outside site), Ordinance Article 45 No. 5 (outside site))

*Please refer to the following organizations about analysis organization when requesting water quality measurement to the outside.

Inquiries and introductions of institutions (traders) that conduct water quality analysis
Contact informationTEL
Yokohama City Environmental Technology Council (http://www.yokokankyo.com/ (outside site))

045-782-1170

Kanagawa Environmental Measurement Council (https://shinkankyou.com/ (outside site))

045-790-5280

Table of measurement number
Water quality itemsNumber of measurements
Cadmium and its compounds
Cyanide compounds
Organic phosphorus compounds
Lead and its compounds
Hexavalent chromium compounds
Arsenic and its compounds
Mercury and alkyl mercury and other mercury compounds
Polychlorinated biphenyl
Selenium and its compounds
At least once every drainage period that does not exceed 14 days

Boron and its compounds
Normal element and its compounds
(If the average amount of effluent per day is less than 50 cubic meters)

At least once per drainage period that does not exceed one month

Boron and its compounds
Normal element and its compounds
(When the average amount of effluent per day is 50 cubic meters or more)

At least once every drainage period that does not exceed 14 days
Trichloroethylene
Tetrachloroethylene
Dichloromethane
Carbon tetrachloride
1,2-dichloroethane
1,1-dichloroethylene
Cis-1,2-dichloroethylene
1,1,1-trichloroethane
1,1,2-trichloroethane
1,3-dichloropropene
Chiuram
Zimazine
Thiobencarb
Benzene
1,4-dioxane
At least once per drainage period that does not exceed one month
Dioxins
(Refers to dioxins in Article 2 (outside site) of the Law Concerning Special Measures against Dioxins (Act No. 105 of 1999))
1 or more times for each drainage period not exceeding one year
Temperature
Hydrogen ion concentration
At least once a day during the drainage period

Contains ammonia nitrogen, nitrite nitrogen, nitrite nitrogen, nitrate nitrogen, etc.
Nitrogen content (*1)
Phosphorus content (*1)
(If the average amount of effluent per day is less than 20 cubic meters)

At least once every drainage period that does not exceed three months

Contains ammonia nitrogen, nitrite nitrogen, nitrite nitrogen, nitrate nitrogen, etc.
Nitrogen content (*1)
Phosphorus content (*1)
(When the average amount of effluent per day is between 20 cubic meters and less than 50 cubic meters)

At least once every drainage period that does not exceed two months

Contains ammonia nitrogen, nitrite nitrogen, nitrite nitrogen, nitrate nitrogen, etc.
Nitrogen content (*1)
Phosphorus content (*1)
(When the average amount of effluent per day is 50 cubic meters or more)

At least once per drainage period that does not exceed one month

Biochemical Oxygen Demand
The mass of suspended matter
Normal hexane extract content
(Limited to the content of animal and plant oils and fats.)
(If the average amount of effluent per day is less than 20 cubic meters)

At least once every time a drainage period not exceeding one year

Biochemical Oxygen Demand
The mass of suspended matter
Normal hexane extract content
(Limited to the content of animal and plant oils and fats.)
(When the average amount of effluent per day is between 20 cubic meters and less than 50 cubic meters)

At least once every drainage period that does not exceed three months

Biochemical Oxygen Demand
The mass of suspended matter
Normal hexane extract content
(Limited to the content of animal and plant oils and fats.)
(When the average amount of discharged water per day is 50 cubic meters or more and less than 2,000 cubic meters)

At least once every drainage period that does not exceed two months

Biochemical Oxygen Demand
The mass of suspended matter
Normal hexane extract content
(Limited to the content of animal and plant oils and fats.)
(When the average amount of effluent per day is 2,000 cubic meters or more)

At least once every drainage period that does not exceed 14 days

Normal hexane extract content
(Limited to the content of mineral oil.)
(If the average amount of effluent per day is less than 20 cubic meters)

At least once every drainage period that does not exceed three months

Normal hexane extract content
(Limited to the content of mineral oil.)
(When the average amount of effluent per day is between 20 cubic meters and less than 50 cubic meters)

At least once per drainage period that does not exceed one month

Normal hexane extract content
(Limited to the content of mineral oil.)
(When the average amount of effluent per day is 50 cubic meters or more)

At least once every drainage period that does not exceed 14 days

Others
(Copper, zinc, soluble iron, soluble manganese, chromium, phenols, nickel, fertile consumption, appearance)
(If the average amount of effluent per day is less than 50 cubic meters)

At least once per drainage period that does not exceed one month

Others
(Copper, zinc, soluble iron, soluble manganese, chromium, phenols, nickel, fertile consumption, appearance)
(When the average amount of effluent per day is 50 cubic meters or more)

At least once every drainage period that does not exceed 14 days

(Remarks) *1
Business sites that exclude Tokyo Bay and public water bodies (hereinafter referred to as the "Tokyo Bay Basin") with an average daily discharge of 50 m3 or more and are discharged into the water reclamation center. Apply to

(Note) Water Reclamation Center whose discharge destination is the Tokyo Bay basin: Northern 1st, Northern 2nd, Kanagawa, Chubu, Southern, Kanazawa, Kohoku, Tsuzuki

Water Reclamation Center with discharges outside the Tokyo Bay basin: West, Sakae Daiichi, Sakae Daini

Inquiries to this page

Water Quality Division, Sewerage and Rivers Bureau Sewerage Facilities Department

Phone: 045-671-2835

Phone: 045-671-2835

Fax: 045-550-4183

E-Mail address [email protected]

Return to the previous page

Page ID: 164-465-417

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews