Minami Honmoku Futo No. 5 Block Disposal Site Development Project 2

Last updated on April 1, 2024.

Fifth Block Disposal Site Development Project

  • Water-shilled seawall

The structure of the imperfection revetment is divided into the "main body part" that separates the water area where waste is invested and the surrounding area, and the "base part" that supports the main body part.
In designing, we are working to reduce construction costs as much as possible by devising a method of landfilling waste (*).

(※) In some sections, we plan to reclaim the soil generated outside construction in line with the input of waste inside the impermeable revetment so that no large force is applied to the impermeable revetment from one side. (Equal Landfill)
・Foundation part
We will improve the ground using the deep mixing process (CDM*) method. (*Obbreviation of Cement Deep Mixing)
By agitating soft earth and sand (conventional ground) deposited under the surface of the water with cement, it is strengthened so that the main body can be supported, and the water-shielding property is ensured.
・Main part
The system will be developed in two types of structural forms: steel sheet cell type and cason type.

Steel plate cell type

In the section where the outside of the imperfection revetment is reclaimed prior to construction soil, a large force is applied from one side, so we are examining to withstand the pressure and selecting a steel sheet cell type.
(structure)
A huge steel plate "cylindrical" is installed, sand and rocks are poured inside to pack the inside.
In addition to installing these continuously, each "cylindrical" is connected with steel plate to form a seawall.
Between the steel sheet cell and the foundation part, a material that is deformed so that it adheres to the shape of the foundation ground to ensure water insulation.
(Steel cell size: 14m in diameter, 14.6m in height)
Steel plate cell type


Cason type

For areas where “Equal Landfill” is performed, we have selected a cathson type that can have a slim structure.
(structure)
A huge reinforced concrete box (caisson) will be installed and packed inside.
These are installed continuously to form a revetment.
The impermeability between the caisson and the foundation, and between the caisson and the caisson, is ensured by using a material that deforms to adhere to the shape between the gaps.
(Size of caisson: 20m long, 9.5m wide, 15m high)
Cason type

  • Progress

Fiscal 2004 to fiscal 2006

Environmental assessment

→ Procedures (Green Environment Bureau Environmental Impact Assessment Division)

2007
We started construction.
・Ground improvement work

2008
Ground improvement work

2009
Ground improvement work

2010
Ground improvement work

2011
Ground improvement work, main body production work

2012
Ground improvement work, main body production work, dredging work

2013
Ground improvement work, main body production work, dredging work

2014
Ground improvement work, main body production and installation work, dredging work

2015
Ground improvement work, main body production and installation work, dredging work

△To the previous page

Inquiries to this page

Shinhonmoku Business Promotion Division, Port and Harbor Bureau Policy Coordination Department

Phone: 045-671-7390

Phone: 045-671-7390

Fax: 045-550-4186

E-Mail address [email protected]

Return to the previous page

Page ID: 466-735-172

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews